General Info
- Report Type: HCV Assessment
- Country: Indonesia
- Evaluation Status: Closed
- Organisation commissioning assessment: GAR- PT CNG
- Purpose of assessment: RSPO New Planting
First Submission
- Date of submission: August 24, 2017
- Date evaluation results sent to Assessor: January 16, 2018
- Submission evaluation result: Unsatisfactory
First Re-Submission
- Date received from assessor: January 30, 2018
- Date evaluation results sent to assessor: February 22, 2018
- Evaluation result: Satisfactory
Final report result: Satisfactory
- Date final results published: February 22, 2018
- Size of Development Area (in ha): 891.90
- Total Conservation Area (in ha): 328.80
- HCV management area (in ha): 328.80
- HCVs identified: HCV 1, HCV 3, HCV 4, HCV 5, HCV 6