General Info

  • Report Type: Integrated HCV-HCSA Assessment
  • Country: Indonesia
  • Evaluation Status: Closed
  • Organisation commissioning assessment: PT. Prisma Cipta Mandiri
  • Purpose of assessment: RSPO New Planting

First Submission

  • Date of submission: April 23, 2020
  • Date evaluation results sent to Assessor: July 9, 2020
  • Submission evaluation result: Unsatisfactory

First Re-Submission

  • Date received from assessor: August 19, 2020
  • Date evaluation results sent to assessor: October 8, 2020
  • Evaluation result: Unsatisfactory

Second Re-Submission

  • Date received from assessor: November 30, 2020
  • Date evaluation results sent to assessor: December 7, 2020
  • Evaluation result: Satisfactory

Final report result: Satisfactory

  • Date final results published: December 7, 2020
  • Size of Development Area (in ha): 11,720.73
    • Total Conservation Area (in ha): 1,534.33
    • HCV area identified (in ha): 1,515.29
    • HCV management area (in ha): 1,534.33
    • HCS Forest (in ha): 414.81
  • HCVs identified: HCV 1, HCV 3, HCV 4, HCV 5, HCV 6
View PDF Public Summary (English) View PDF Public Summary (Original)