General Info
- Report Type: HCV Assessment
- Country: Sierra Leone
- Evaluation Status: Closed
- Organisation commissioning assessment: Goldtree Limited
- Purpose of assessment: RSPO New Planting
First Submission
- Date of submission: June 21, 2017
- Date evaluation results sent to Assessor: July 24, 2017
- Submission evaluation result: Unsatisfactory
First Re-Submission
- Date received from assessor: August 25, 2017
- Date evaluation results sent to assessor: September 29, 2017
- Evaluation result: Satisfactory
Final report result: Satisfactory
- Date final results published: September 29, 2017
- Size of Development Area (in ha): 1,033.00
- Total Conservation Area (in ha): 222.96
- HCV area identified (in ha): 222.96
- HCV management area (in ha): 222.96
- HCVs identified: HCV 1, HCV 3, HCV 4, HCV 5, HCV 6